Electrical demand calculation: demand factor, diversity and reserve
An electrical demand study turns the connected load of every circuit into a realistic maximum demand by applying demand, service and diversity factors, then rolls it up through panels and transformers with a reserve margin.
When to use
Run a demand study early in any electrical project, right after you have a load schedule with the nameplate ratings of motors, lighting, sockets and process loads. It converts the sum of nameplate ratings — which no installation ever draws at once — into the maximum demand the feeders, panels, transformers and generators must actually carry. Use it to size the upstream transformer and standby generator, to pick feeder ampacity and the main circuit breaker of each board, to confirm a panel has spare capacity for future loads, and to reconcile the metered demand of an existing plant against the design. It is the bridge between the equipment list and every protection, cable and source-sizing decision downstream.
What an electrical demand study is
A demand study answers a deceptively simple question: how much power will this installation actually draw at its worst moment? The naive answer — add up every motor, lamp and socket on the equipment list — gives the connected (installed) load, a number no real plant ever reaches, because loads do not all run at full rating at the same instant. The useful answer is the maximum demand: the connected load filtered through a chain of factors that model how the installation truly behaves.
That demand is the single most consequential number in the project. It sizes the upstream transformer and the standby generator, sets the ampacity of every feeder and the frame of every main breaker, and decides whether a board has room for the loads still on the drawing. Get it too low and the source trips or burns; get it too high and you have paid for copper and iron that will never carry current — and a transformer running far below its nameplate sits at a poor power factor.
From nameplate to installed power
The study works bottom-up, one load at a time. A motor nameplate gives mechanical shaft power (in kW or cv); the grid must supply more than that, because the motor itself has losses and draws reactive power. Two conversions bring the nameplate to the electrical installed value:
S_inst = (P_shaft / η) / cosφ
Dividing by the efficiency η turns shaft power into electrical active power (the motor’s losses are real load on the cable); dividing by the power factor cosφ turns active power [kW] into apparent power [kVA], which is what conductors and transformers are rated for. A load already specified in kVA (a lighting board, an electronic panel) skips the efficiency step — it is already an electrical figure.
From installed power to demand
No load runs at its full installed power continuously. The demand factor FD captures the fraction it actually draws at peak. The demanded power of a single load is simply:
S_dem = S_inst · FD
The service factor FS does not enter here. FS (typically 1.15 for continuous motors) is the motor’s permissible thermal overload, not a load of regime — it is consumed downstream by the protection (it caps the overload-relay / motor-breaker setting, 125 % FLC when FS ≥ 1.15), while the running margin at the branch and the global expansion margin cover the rest. Folding FS into the demand inflates every level of the tree by ~15 %.
A load declared as standby (reserve) duty contributes zero — by definition it is not running while its duty partner is. This is the single most common source of oversizing: counting both halves of a redundant pair.
Rolling demand up the tree
Loads feed panels; panels feed other panels and transformers; transformers feed the grid or a generator. The study walks this tree from the leaves up, accumulating kW, kVAr and kVA. At a panel, two project factors are applied to the sum of its children:
S_panel = (Σ S_dem,i) · g · (1 + r)
The diversity (simultaneity) factor g is below 1 because the individual peaks of many circuits do not coincide — the more, smaller circuits a board aggregates, the lower g can safely be. The reserve fraction r then adds spare capacity (often 20 %) so the board and its source can absorb future loads. A transformer node is pass-through: it simply sums its children, with no extra diversity or reserve, because those were already applied at the panels below it.
A critical discipline here: diversity is applied once, at the panel that genuinely aggregates independent circuits — not compounded at every level. Multiplying a factor below 1 at each tier of a deep tree silently drives the source dangerously undersized.
Current, source and emergency demand
Once a panel’s demand in kVA is known, the line current that sets its main breaker and incoming feeder follows directly:
I = S · 1000 / (√3 · V) for a three-phase board (use S·1000/V single-phase).
To pick the transformer or generator, a 15 % expansion margin is added over the rolled-up demand and the result is rounded up to the next standard commercial rating. The same roll-up, restricted to the loads flagged essential, yields the emergency demand — the kVA a standby generator must carry — which ISO 8528 then refines for motor inrush and step loading.
Reading the result
A healthy demand study shows each level loaded comfortably below its nameplate capacity:
- Per panel, the occupancy (demand ÷ capacity) should leave the declared reserve free — green well under 80 %, amber as it approaches the limit, red above 100 %.
- Per transformer, the rolled-up demand plus the 15 % expansion margin should land on a standard size with the spare capacity you intended, not scrape the next size up.
- Per generator, the essential-load sum must include the largest motor’s starting step, not just the steady demand.
- Installed vs demanded, the gap between the two (here ~87 kVA installed against ~70 kVA demanded before diversity) is the tangible value of the study — it is the capacity you did not have to buy.
Practical cautions
- Group by load nature. Lighting, motors, sockets and process loads each have their own demand-factor range; a single plant-wide FD hides the real picture.
- Keep the service factor out of the demand. FS sizes the motor’s overload protection (relay / breaker setting), not the demanded power; the demand uses FD only.
- Exclude standby duty. Reserve units are covered by their duty partners; counting them inflates source and generator alike.
- Apply diversity once. At the aggregating panel — never compounded level by level.
- Align factors with the standard. NBR 5410 (and IEC 60364) frame demand and utilization factors for low voltage; IEEE 141 gives industrial guidance; ISO 8528 governs the generator rating.
Followed in this order — nameplate to installed, installed to demanded, roll-up with diversity and reserve, then current and source — the demand study produces the load schedule that every downstream decision (cable, protection, transformer, generator) depends on, and keeps the installation both safe and economical.
Formulas and fundamentals
S_inst = (P_shaft / η) / cosφ Apparent power [kVA] a motor draws from the grid. P_shaft is the mechanical shaft rating [kW] (1 cv = 0.7355 kW), η the motor efficiency [p.u.] and cosφ the power factor. Dividing by η accounts for motor losses; dividing by cosφ converts active power [kW] to apparent power [kVA]. Non-motor loads given directly in kVA skip the efficiency step.
S_dem = S_inst · FD Maximum demand of a single load [kVA]. FD is the demand factor (fraction of the installed power actually drawn at peak). Standby (reserve-duty) loads contribute zero. Reactive and active parts scale by the same factor FD. The service factor FS does not enter the demand: it is the motor's thermal overload margin and is consumed downstream by the protection (overload relay / motor breaker setting), not by load sizing.
S_panel = (Σ S_dem,i) · g · (1 + r) Demand of a board built up from its children [kVA]. Σ S_dem,i is the sum of the demanded powers of the circuits fed by the panel, g the diversity/simultaneity factor (< 1, because not all circuits peak together) and r the reserve fraction (e.g. 0.20 for +20 % spare capacity). A transformer node is pass-through: it just sums its children without g or r.
I = S · 1000 / (√3 · V) Line current [A] drawn at the panel busbar. S is the panel demand [kVA] and V the line-to-line voltage [V]. Single- and two-phase boards use I = S·1000 / V. This current sets the main breaker frame and the incoming feeder section.
S_source ≥ S_dem · 1.15 → next commercial kVA Transformer or generator rating [kVA]. A 15 % expansion margin is added over the rolled-up demand, then rounded up to the next standard size (transformers: 75, 112.5, 150, 225, 300, 500… kVA; generators: 40, 75, 110, 150, 180, 250… kVA, ISO 8528).
Standards & methods
- ABNT NBR 5410 — Low-voltage electrical installations (demand and utilization factors)
- ABNT NBR 14039 — Electrical installations above 1 kV (medium voltage)
- IEC 60364-1 — Low-voltage electrical installations, fundamental principles
- IEEE 141 (Red Book) — Recommended practice for electric power distribution for industrial plants
- ISO 8528-1 — Reciprocating internal-combustion engine driven generating sets (rating)
Typical reference values
| Quantity | Typical range | Note |
|---|---|---|
| Demand factor — lighting | 0.60 to 1.00 | Process/continuous lighting near 1.0; office/intermittent lighting lower. |
| Demand factor — motor loads | 0.70 to 1.00 | Continuous-duty motors high; intermittent or batch loads lower. |
| Diversity / simultaneity factor (panel) | 0.70 to 1.00 | Few large feeders → near 1.0; many small terminal circuits → lower. |
| Reserve / spare capacity | 10 % to 25 % | 20 % is common on main boards to allow future loads without replacing gear. |
| Power factor (uncorrected) | 0.80 to 0.95 | Induction motors ~0.85; resistive/electronic loads higher. Sets the kVA from kW. |
| Motor efficiency (IE3) | 0.90 to 0.96 | Rises with motor size; converts shaft kW to electrical input. |
Worked example
440 V process panel feeding four circuits
Inputs
- Motor 1 (continuous)
- 30 kW, η 0.95, cosφ 0.87, FD 0.90 kW
- Motor 2 (intermittent)
- 15 kW, η 0.93, cosφ 0.86, FD 0.80 kW
- Lighting board
- 10 kVA, cosφ 0.92, FD 0.66 kVA
- Socket / general board
- 20 kVA, cosφ 0.95, FD 0.50 kVA
- Diversity factor (panel)
- g = 0.90 p.u.
- Reserve
- r = 20 %
Results
- Σ installed power
- ≈ 87.0 kVA
- Σ demanded power (loads)
- ≈ 65.4 kVA
- Panel demand (× g × 1+r)
- ≈ 70.6 kVA
- Demand current (3∅, 440 V)
- ≈ 93 A
- Suggested transformer
- 112.5 kVA
Each load is first taken to installed kVA: motor 1 = (30/0.95)/0.87 ≈ 36.3, motor 2 = (15/0.93)/0.86 ≈ 18.7, lighting = 10/0.92 ≈ 10.9, sockets = 20/0.95 ≈ 21.1 — about 87 kVA installed. Applying the demand factor FD to each (36.3·0.9 ≈ 32.7; 18.7·0.8 ≈ 15.0; 10.9·0.66 ≈ 7.2; 21.1·0.5 ≈ 10.5) gives roughly 65.4 kVA of demanded power that, summed straight, already drops below the 87 kVA installed. The service factor is not applied here — it belongs to the motor protection, not the demand. The panel then applies diversity and reserve: 65.4·0.90·1.20 ≈ 70.6 kVA, drawing about 93 A on a 440 V three-phase bus. With a 15 % expansion margin (≈ 81.2 kVA) the next standard transformer is 112.5 kVA, leaving healthy spare capacity for the declared 20 % reserve plus future growth.
Common mistakes
- Sizing the transformer on the sum of nameplate ratings (installed load) instead of the demand — this oversizes the source, wastes capital and worsens the no-load power factor.
- Applying a single demand factor to a whole plant instead of grouping by load nature (lighting, motors, sockets, process) — each category has its own FD.
- Folding the service factor into the demand: FS is the motor's thermal overload margin and belongs to the protection setting (overload relay / motor breaker), not to the demand — multiplying it in inflates every level of the tree.
- Counting standby (reserve) loads in the demand: a 100 %-redundant pump pair must contribute only one running unit, not both.
- Multiplying every level by a diversity factor < 1, compounding it down the tree until the source is dangerously undersized — diversity applies once, at the panel that aggregates the circuits.
- Sizing the standby generator on the steady demand only, ignoring motor starting (inrush) and the largest-motor step-load that ISO 8528 governs.
Frequently asked questions
What is the difference between installed load and demand?
Installed (or connected) load is the sum of all nameplate ratings — the worst case if every device ran at full power simultaneously, which never happens. Demand is the realistic maximum the installation actually draws, obtained by multiplying each load by its demand factor and then aggregating circuits with a diversity factor. Feeders, panels and transformers are sized on demand, never on installed load.
How do the demand factor and the diversity factor differ?
The demand factor (FD) applies to a single load or load group: it is the fraction of its installed power that is actually drawn at peak. The diversity (or simultaneity) factor applies when several circuits are aggregated at a panel: it accounts for the fact that their individual peaks do not coincide in time. FD reduces each load; diversity reduces the sum at the busbar.
Where does the service factor enter, if not in the demand?
The service factor (≥ 1, typically 1.15 for continuous motors) is the motor's permissible thermal overload — not a load of regime — so it does not multiply the demand. It is consumed by the protection: it sets the ceiling of the overload-relay / motor-breaker setting (125 % FLC when FS ≥ 1.15, otherwise 115 %). The demand uses the demand factor FD only; the motor running margin is covered downstream at the branch (125 % FLC) and by the global expansion margin.
Should standby (reserve) equipment be counted in the demand?
No. A load flagged as reserve duty (for example the redundant unit of a 100 %-spare pump pair) does not run during normal operation and contributes zero to the demand roll-up. Counting it would oversize the transformer and the generator. Only the running units are summed; the standby unit is covered because its rating equals the duty unit it replaces.
How does the reserve percentage affect the result?
The reserve (spare-capacity) fraction is applied at the panel after diversity: S_panel = Σ × g × (1 + r). A 20 % reserve sizes the board and its source to carry the present demand plus future loads without replacing gear. It is a project decision, not a code factor, and is declared per panel.
Why add 15 % before choosing the transformer size?
The 15 % expansion margin keeps the source comfortably below its nameplate at peak, away from continuous full-load operation that shortens insulation life and erodes efficiency, and reserves room for plant growth. After adding it, the demand is rounded up to the next standard commercial rating (75, 112.5, 150, 225, 300 kVA…), so the chosen transformer always has headroom over the computed demand.
Glossary
- Connected (installed) load
- Sum of the nameplate ratings of every load on a circuit or panel, in kVA — the maximum if everything ran at once.
- Maximum demand
- Realistic peak power the installation actually draws, obtained by applying demand and diversity factors to the connected load.
- Demand factor (FD)
- Ratio of the maximum demand of a load to its installed power; always ≤ 1. Captures that loads rarely run at full rating.
- Diversity / simultaneity factor
- Factor (< 1) applied when aggregating several circuits at a panel, because their individual demand peaks do not coincide in time.
- Service factor (FS)
- Permissible thermal overload multiplier of a motor (typically 1.15); it sizes the overload protection, not the demand (which uses FD only).
- Reserve capacity
- Spare margin (e.g. +20 %) added at a panel so the board and its source can absorb future loads without being replaced.
- Power factor (cosφ)
- Ratio of active power (kW) to apparent power (kVA); converts a load's useful power into the apparent power the system must carry.